Saturday, May 3, 2008

Subfloor, lighting rough in, drywall work

Work continued on Sunday, bright and early again. The work was slightly less dramatic than the demo day. Ian and Tim installed the subfloor, patched the drywall and roughed in the electric for the recessed lights, pendant and undercabinet lighting, among other activities that I'm probably not aware of. During the rest of the week, Tim worked solo with me on clean-up. He finished the drywall work, and further secured the subfloor.


Ian roughing in the electricity for the recessed lighting from the kitchen.
















Timmy roughing in the electric from the attic.